CEEC Energy Storage System Powers Wind Energy Transition in Altay, Xinjiang

Operational Impact‌

  1. Energy & Environmental Benefits:
    • Annual generation: 780 million kWh, powering 260,000 households.
    • Annual carbon reduction: 618,000 tons, SO₂ reduction: 20,300 tons.
  2. Technical & Economic Breakthroughs:
    • Curtailment reduced from 8% to 1.5%, grid flexibility improved by 50%.
    • Green power cost: 0.35-0.38 RMB/kWh, yielding annual revenue of ~270 million RMB.
  3. Industry Leadership:
    • Xinjiang’s first gigawatt-scale wind-storage project, recognized as a national innovation model.
    • Created 800+ local jobs, fostering clean energy clusters and supporting Xinjiang’s energy hub ambitions.

Date

August , 2022

Client

Altay

Category

PV & Wind EssProjects

Location

Xinjiang

Share This Project :

Project Context

   Located in northern Xinjiang, Altay is a rare hub for hydro, wind, and solar resources, offering ideal conditions for clean energy development. CEEC’s 250MW wind-storage hybrid project in Jeminay County addresses grid integration challenges by deploying a 25MW/50MWh Energy Storage System (ESS), complying with policy requirements (10% capacity, 2-hour discharge) to enable large-scale renewable energy integration

Engineering Solution

38188fb8ec6d4b998a61471e6006db1b (1)

  CEEC adopted an intelligent wind-storage coordination system:

Share This Project :

Free Consultation If You Want Build New Project With Us

Lorem ipsum dolor sit amet, consectetur adipiscing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo dolore magna

Get a fast response from our expert

Let's have a chat